Reactive to preventive in 105 checks
A technician visits a site because something broke. The visit is paid for either way. So the cost of checking everything else on that visit is close to zero.
That one idea turned a reactive service model into a preventive one at Tessol.
The checklist
I built a preventive maintenance checklist with 105 items. Every visit, the technician runs the full list, whatever the complaint was. Failed items are logged.
What changes
- The next complaint visit arrives with the right parts, because the failed items are already known.
- The next visit verifies the last visit's open items, so nothing is quietly dropped.
- Complaints become less frequent because small faults are caught early.
The numbers across 5 cities
- Complaints breaching the 72 hour TAT fell from 32% to 6%.
- Complaints resolved the same day rose from 29% to 46%.
The objection
The obvious objection is that a long list slows each visit. It does, a little. The second visit it removes costs far more than the extra minutes.
If a person is already standing at the asset, ask what else you will wish you had checked.